欢迎来到计算机考试题库网 计算机题库官网
logo
全部科目 > 软件认证工程师考试 > 思科认证考试 > CCNA系列认证 > CCNA(650-393)

单项选择题

Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:()。

    A.ensure that it receives detailed network diagrams
    B.reduce the risk of downtime due to facilities-related problems
    C.ensure end-user support immediately after the launch of a new system
    D.confirm project roles and responsibilities, as well as milestone dates

点击查看答案

相关考题

微信小程序免费搜题
微信扫一扫,加关注免费搜题

微信扫一扫,加关注免费搜题