欢迎来到计算机考试题库网 考试题库官网
全部科目 > 计算机软件水平考试 > 信息系统项目管理师 > 高级信息系统项目管理师 > 专业英语

单项选择题

() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.projectacceptance
    B.scopeverification
    C.scopedefinition
    D.WBS Creation

点击查看答案&解析