On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating
    B.cost estimating
    C.project planning
    D.schedule development

点击查看答案