Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer
点击查看答案&解析
相关考题
-
单项选择题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Riskldentification
B.Quantitative RiskAnalysis
C.Qualitative RiskAnalysis
D.Risk Monitoring and Control -
单项选择题
Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.
A.Integration
B.Time
C.Planning
D.Communication -
单项选择题
()is a category assigned to products or services having the samefunctional use but different technical characteristics. Itisnotsameasquality.
A.Problem
B.Grade
C.Risk
D.Defect