单项选择题
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
点击查看答案&解析
相关考题
-
单项选择题
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the projects requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing -
单项选择题
The()defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone -
单项选择题
()means that every project has a definite beginning and a definite end.
A.Projectphase
B.Unique
C.Temporary
D.Closure