欢迎来到计算机考试题库网 考试题库官网
全部科目 > 计算机软件水平考试 > 信息系统项目管理师 > 高级信息系统项目管理师 > 专业英语

单项选择题

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.

    A.time estimating
    B.cost estimating
    C.project planning
    D.schedule development

点击查看答案&解析

相关考题