()is the process of obtaining the stakeholders’ formal acceptance of the completed project scopE. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation