单项选择题
Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT
B.Resourceleveling
C.Schedulecompression
D.Critical chain method
点击查看答案&解析
相关考题
-
单项选择题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating -
单项选择题
The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating -