单项选择题
Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
相关考题
-
单项选择题
The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating -
单项选择题
The Unified Modeling Language is a standard graphical language for modeling object-oriented software()can show the behavior of systems in terms of how objects interact with each other.
A.Classdiagram
B.Componentdiagram
C.Sequencediagram
D.Use case diagram -
单项选择题
()is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
A.Method
B.Polymorphism
C.Inheritance
D.Encapsulation