单项选择题
The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.
A.work performance information
B.scope statement
C.changerequests
D.process analysis
点击查看答案&解析
相关考题
-
单项选择题
The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
A.executedin
B.inspectedin
C.check-in
D.look-in -
单项选择题
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer -
单项选择题
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
A.Riskldentification
B.Quantitative RiskAnalysis
C.Qualitative RiskAnalysis
D.Risk Monitoring and Control