单项选择题
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
点击查看答案&解析
相关考题
- 单项选择题 The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
- 单项选择题 The()describes, in detail, the project's deliverables and the work required to create those deliverables.
- 单项选择题 The()provides the project manager with the authority to apply organizational resources to project activities.
- 单项选择题 The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the projects requirements.
- 单项选择题 The()defines the phases that connect the beginning of a project to its end.
- 单项选择题 ()means that every project has a definite beginning and a definite end.
- 单项选择题 () is the process of obtaining the stakeholders formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
- 单项选择题 () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
- 单项选择题 () is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype
- 单项选择题 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.